Waitomo Caves Visitor Centre


The Waitomo Caves are a popular tourist attraction located near Otorohanga in the Central North Island Region. Following the destruction of the existing visitor centre by fire in 2005, Hawkins was engaged to construct a new more extensive and modern visitor centre.

The new building is a primarily timber-framed structure comprising three levels that incorporate offices, a retail area, a restaurant with a full commercial kitchen, ticketing area, exhibition centre and various amenities. A lift was installed providing access to each level. The entire building is covered by a large timber-framed, curved ETFE canopy structure, the first of its kind in New Zealand.

The floors, decks, walls and roof of the visitor centre are timber framed with structural steel strengthening members. The building was clad primarily in redwood boarding with Titan Board accents. The main public toilet block has a concrete floor, sloping precast concrete walls and an in situ concrete roof.

As the construction of a canopy structure of this type had never been attempted before, Hawkins had to pioneer a strategy for its construction. A prototype was developed prior to construction to examine in detail how construct the frame: a collaborative process with the engineer and architect. It was imperative that the curved beams were manufactured with the utmost accuracy. Also, extreme diligence had to be taken when setting out.

The overhead canopy structure comprises a series of curved laminated timber beams running in opposite directions and crossing over each other at nodal points. The roof is completed with translucent inflatable ETFE pillows, which provide a watertight covering and follow the curve of the canopy.

The challenge for the project team was to manage and construct this complex structure on a steep and confined site, in often less than desirable weather conditions, to a tight programme while keeping the facility operational.

Hawkins was presented with a steeply sloping site immersed in vegetation and large trees. Once cleared, the site had to be benched to create a base for the three levels and MSE soil-retaining walls were constructed at each level. Due to the time of year the project commenced, the bulk earthworks were delayed by wet weather; however, Hawkins managed to accelerate the programme so as not to jeopardise the strict completion deadline.

A stream running across the base of the site meant strict environmental procedures had to be put in place. A permanent swale drain, running the length of the site, was constructed early to provide drainage at the low end. This discharged into a large soak hole and was covered temporarily with filter cloth to prevent sediment blockage. Various temporary trenches, earth bunds, soakage pits and silt fences were also constructed to control run off.

The visitor centre is self-sufficient in terms of water supply, with canopy rainwater being discharged via a landscaped swale, with peak overflow to the river and water supply being taken from the river after local filtration and treatment. The centre also uses water efficient sanitary fixtures.

Being an international tourist attraction, the Waitomo Caves had to remain operational throughout construction. Hawkins was able to ensure that day-to-day operations and public safety were maintained at all times. This was achieved through constant co-ordination with the operations staff, carefully placed hoardings and fencing and the construction of various temporary stair structures and tracks.

Temporary amenities were setup utilising a Portacom, which was dressed up to provide a visually acceptable façade to the public.

In order to conform to the extremely tight construction programme, the installation of internal finishings had to commence before the building was complete or watertight. Temporary waterproofing membranes were installed over the exposed floors above each level to create a waterproof environment.

Due to the extremely confined nature of the site, construction had to be carefully staged to ensure adequate access was available for cranes and other heavy machinery at essential stages of the build. The canopy was constructed from the innermost end of the site to the outer. As the front of the site was in line with the road, appropriate traffic control measures had to be maintained at all times.

Now visitors to the caves, both local and international, are greeted by a world-class, modern visitor centre with an impressive and unique construction and appearance.

The project was successful handed over to THL in May 2010.

 


News

  • March 26, 2012

    New AMI Stadium Gets The Thumbs Up

    Read more
  • February 07, 2012

    Another Project at Waikato Hospital

    Read more
  • December 15, 2011

    Hawkins Construction And Te Runanga O Ngai Tahu Establish Partnership

    Read more